Upper Scull Creek Phase II

Image of  upper Scull Creek drainage area affected

What is the Project?

Continuation of the Upper Scull Creek project to address flooding in the vicinity of N Olive Ave and E Johnson Street, between Rebecca Street and Walnut Avenue (Ward 1). Plans include include additional underground storm drainage to alleviate street flooding and property damage.

Why is it Important?

To address neighborhood wide flooding of streets that is also causing damage to private property.

What is the Status?

Pending

How is it Funded?

Funding for this project comes from the Bond issue passed by voters in April, 2019.